Mining commences at Kiniéro as project tracks towards first gold in Q4 CY2025

Next article :

  • Press Release
Financial Results Q1-2025

Robex Q1 2025: Kiniero on track for Q4 gold; ASX listing June 5; raised A$120M; mined 12,892 oz gold; ops (...)

Share our article on

You’re interested into our business or you may have an interesting opinion to share?

Join us Online

Highlights:
• Robex’s Kiniero Gold Project, Guinea, remains on track and budget for first gold pour in Q4 CY25.
• The Kiniero project remains LTI free (lost time injury) with 4,857,704 hours complete to 30 September 2025.
• Mine development activities are tracking according to plan; Mining has commenced on day and night shift
with delivery of ore to the Run-of-Mine (ROM) Pad.
• Drilling and blasting contractor mobilised to site, with the first blast planned this month.
• Construction of the Tailings Storage Facility is progressing on schedule.
• Field erected tankage is 99% complete with only painting outstanding.
• Oxide crusher ROM wall and power station remaining footings were poured in early October.
• Concrete contract is complete and demobilisation commenced.
• All project fabrication materials platework, steelwork, piping and electrical materials have arrived at site.
• SMP (Structural, Mechanical & Piping) works progressing, with 50% of structural steel erected/preassembled.
• SAG and Ball Mill assembly of major components is nearing completion.
• Power station is progressing on schedule; low voltage motor control centres (LV MCCs) received and installed.
• Fuel storage facility tankage erection progressing on schedule.